A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?
A) A B
B) A B D
C) A C D
D) Cannot be determined from the information given
Correct Answer:
Verified
Q35: The shortest possible time to complete an
Q36: When estimating the probability of completing a
Q37: A project's completion time variance is calculated
Q38: The third step to crash a project
Q39: If an activity has a late start
Q41: Project risks that are mostly within company
Q42: Lack of communication among key personnel would
Q43: Project risks outside of company control such
Q44: Poor supplier selection is an example of
Q45: Three critical activities (A, B, and C)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents