Three critical activities (A, B, and C) have crash costs per hour of $100, $150, and $200, respectively. Which of these activities should be crashed first?
A) A
B) B
C) C
D) Cannot be determined from the information given
Correct Answer:
Verified
Q40: A project has four activities. Activity
Q41: Project risks that are mostly within company
Q42: Lack of communication among key personnel would
Q43: Project risks outside of company control such
Q44: Poor supplier selection is an example of
Q46: Three activities (A, B, and C) have
Q47: What type of activities should be considering
Q48: Which of the following activities would likely
Q49: Crash cost per period is determined by
Q50: An activity has a normal duration of