Crash cost per period is determined by which of the following equations?
A) (Crash cost) / (Normal cost)
B) (Crash cost - normal cost) / (normal time - crash time)
C) (Normal time - crash time) / (crash cost - normal cost)
D) It is impossible to calculate the crash cost per period for an activity
Correct Answer:
Verified
Q44: Poor supplier selection is an example of
Q45: Three critical activities (A, B, and C)
Q46: Three activities (A, B, and C) have
Q47: What type of activities should be considering
Q48: Which of the following activities would likely
Q50: An activity has a normal duration of
Q51: Which of the following activities would likely
Q52: Project risks that are either inside or
Q53: Project risks that are within company control
Q54: The use of unfamiliar software would be