Unrealistic activity time estimations would be an example of what type of project risk?
A) External
B) Operational
C) Cost
D) Schedule
Correct Answer:
Verified
Q52: Project risks that are either inside or
Q53: Project risks that are within company control
Q54: The use of unfamiliar software would be
Q55: Project risks that are mostly within company
Q56: An activity has a normal duration of
Q58: Poor estimates of activity costs would be
Q59: Which of the following is not a
Q60: Unexpected events that may lead to missed
Q61: Expected activity completion time can be calculated
Q62: The Z value is found by:
A) Z
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents