Expected activity completion time can be calculated (where a = optimistic completion time, b = pessimistic completion time, and m = most likely completion time) as:
A) t = (a + m + b) /3
B) t = (2a + 2m + 2b) /6
C) t = (a + 5m + b) /6
D) t = (a + 4m + b) /6
Correct Answer: