The cost associated with the shortest possible duration for a project activity is referred to as the?
A) Reduced cost
B) Shortest cost
C) Crash cost
D) Activity cost
Correct Answer:
Verified
Q77: Project management software allows for all of
Q78: An activity's early start time minus late
Q79: A project's critical path is the?
A) Longest
Q80: When evaluating a project risk, the project
Q81: Activities with zero slack time are?
A) Rarely
Q83: An activity with a slack time of
Q84: A plan that is put in place
Q85: A government chooses to impose new regulatory
Q86: An activity with a slack time greater
Q87: A critical path activity?
A) Has zero slack
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents