An activity with a slack time of zero?
A) Is a critical path activity
B) Is a possible candidate for crashing
C) Is both a critical path activity and a possible candidate for crashing
D) Is neither a critical path activity nor a possible candidate for crashing
Correct Answer:
Verified
Q78: An activity's early start time minus late
Q79: A project's critical path is the?
A) Longest
Q80: When evaluating a project risk, the project
Q81: Activities with zero slack time are?
A) Rarely
Q82: The cost associated with the shortest possible
Q84: A plan that is put in place
Q85: A government chooses to impose new regulatory
Q86: An activity with a slack time greater
Q87: A critical path activity?
A) Has zero slack
Q88: A contractor indicates that he will be