Assume that an assembly line has three tasks that must be completed (in order, A, B, C, and D) . The tasks have processing times of 8, 12, 9, and 10 minutes per unit, respectively. If the assembly line operates for 500 minutes per day with a desired output of 50 units per day, what is the takt time?
A) 41.7 minutes per unit
B) 10 minutes per unit
C) 62.5 minutes per unit
D) Cannot be determined from the information given
Correct Answer:
Verified
Q79: Product-focused process layouts can lead to all
Q80: A good process-focused layout should seek to?
A)
Q81: A layout in which the manufactured unit
Q82: A machine shop layout is what type
Q83: Assume that an assembly line has three
Q85: Jobs in a process-focused layout tend to
Q86: A house is an example of what
Q87: Focal points in a center aisle location
Q88: Assume that an assembly line has four
Q89: What term is used to describe the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents