A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project?
A) Less than zero
B) 0 − 1.05
C) 1.051 − 1.10
D) 1.11 − 1.15
E) Over 1.15
Correct Answer:
Verified
Q98: The hierarchy of project tasks, subtasks, and
Q99: A project has four activities: A, B,
Q100: Which of the following is not an
Q101: A project has four activities: A, B,
Q102: A project has four activities: A, B,
Q103: An activity has an optimistic time of
Q104: A project has four activities: A, B,
Q105: A project has four activities: A, B,
Q107: A project has four activities: A, B,
Q108: An activity has an optimistic time of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents