In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. All initial inventory values are 0. Use lot-4-lot method for order quantities for all items. What is the low level code (LLC) for B and C?
A) LLC for B is 2 and C is 1.
B) LLC for both B and C is 2.
C) LLC for B is 1 and C is 2.
D) LLC for B is 0 and C is 1.
E) LLC for all items is 1.
Correct Answer:
Verified
Q81: If annual demand is 6,125 units, annual
Q82: In an MRP problem, A is an
Q83: Which of the following is not a
Q84: Which of the following is a dynamic
Q85: In an MRP problem, A is an
Q86: Which of the following is a dynamic
Q87: In an MRP problem, A is an
Q88: Under the lot-for-lot (L4L) lot-sizing technique as
Q89: If annual demand is 12,000 units, annual
Q90: Which of the following is a dynamic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents