![It took 100 hours to produce the first unit and 95 hours to produce the second unit. How many hours are required to produce the eighth unit? [Note: a calculator is required to answer this question.]
A) fewer than or equal to 60 hours
B) greater than 60 hours but fewer than or equal to 75 hours
C) greater than 75 hours but fewer than or equal to 90 hours
D) greater than 90 hours](https://scanned-questions.quizplus.com/1057584.webp)
It took 100 hours to produce the first unit and 95 hours to produce the second unit. How many hours are required to produce the eighth unit? [Note: a calculator is required to answer this question.]
A) fewer than or equal to 60 hours
B) greater than 60 hours but fewer than or equal to 75 hours
C) greater than 75 hours but fewer than or equal to 90 hours
D) greater than 90 hours
Correct Answer:
Verified
Q16: The first two units took 28.5 days
Q17: Which one of the following is an
Q18: Centurion Processing finishes the first unit in
Q19: An 80% learning rate means that the
Q20: Centurion Processing finishes the first unit in
Q22: Tim usually exhibits an 80% learning rate
Q23: The fifth unit took 36.3406 hours to
Q24: A contractor is preparing a bid to
Q25: It took 100 hours to produce the
Q26: A company is introducing a new product.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents