Question 21
Multiple Choice
It took 100 hours to produce the first unit and 95 hours to produce the second unit. How many hours are required to produce the eighth unit? [Note: a calculator is required to answer this question.]
Question 22
Essay
Tim usually exhibits an 80% learning rate for the mechanical tasks he undertakes. His next big project, the fence along the street, will require 35 iterations of the fencepost task. If he has 80 hours available to work on the project, how fast must he perform the first iteration in order to finish all 35 within his allotted time?
Question 23
Multiple Choice
The fifth unit took 36.3406 hours to produce and the eighth unit took only 32.549 hours. If the producer, who shall remain nameless (for obvious reasons) learns at a constant rate, how long did the first unit take?