Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Operations Management Processes
Quiz 17: Supplement J Operations Scheduling
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 101
Multiple Choice
Table J.12 The Feast Janice prepares a medley of pastas for her brother Tony. Each of the pastas must first be rolled and then formed (or in some cases stuffed) before cooking. The required time on each machine in minutes is indicated in the table.
-Janice uses Johnson's rule to schedule her pasta production. How long will it take her to complete the seven pastas?
Question 102
Multiple Choice
Table J.15 Consider the following problem in which four jobs that arrived this morning are to be processed on two machines. They start with the cutting machine and then go to the painting machine. The following processing times are available (in hours) :
-Use the information in Table J.15. What is the makespan through both machines if Johnson's rule is used?
Question 103
Multiple Choice
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs. Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the reduction in makespan for the seven jobs?
Question 104
Multiple Choice
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, on which day will project F be completed?
Question 105
Essay
Lee Beedo, a hip bachelor in Edmond, has a date for Saturday night and finds himself without a thing to wear. Faced with the daunting task of doing enough laundry to fully accessorize during his night out, Lee has sorted his clothes into loads according to fabric and color. Based on his vast experience doing laundry, Lee knows how long each load will take in both the washer and the dryer. He glances at his watch; it is now 2:00 p.m. and he has to have the last load dry by 8:30 p.m. to be there in time. Help Lee develop a schedule that will enable him to make his date on time and depict that schedule using a Gantt chart. Can he make it and, if so, by how much?
Question 106
Multiple Choice
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, how much idle time does Team 2 have from the start of the first project through completion of the seventh?
Question 107
Multiple Choice
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, what is the sequence of projects that minimizes makespan?
Question 108
Multiple Choice
Table J.14 Gable Bakery has five cake orders to be processed today. Each cake has to go through the baking and decorating processes. The baking and decorating times are estimated as follows:
-Use the information in Table J.14. In what sequence should the orders be processed to minimize the total processing time?
Question 109
Multiple Choice
Table J.16 Five jobs are currently waiting to be processed. Each job has to go through Machine 1 first and then Machine 2 before it is completed. The processing times (in hours) for the five jobs on each machine are:
-Use the information in Table J.16. What is the makespan through both machines if Johnson's rule is used?
Question 110
True/False
Acme has an overabundance of machinery available, but most of the workforce has called in sick after the local team's devastating loss on Monday Night Football. This scheduling problem is a labor-limited environment.