Scenario 2.5
A job consists of three distinct work elements that were timed with a highly accurate Swiss watch by a trained industrial engineer. The engineer recorded ten observations listed in the following table. All recorded times are in seconds.
-Use the data in Scenario 2.5 to answer this question. If the rating factor is 10% for all the elements and the allowance is 15% for the whole process, what is the standard process time for the job?
A) 110.69 seconds
B) 82.62 seconds
C) 109.27 seconds
D) 95.02 seconds
Correct Answer:
Verified
Q136: A flowchart traces the flow of all
Q137: A swim lane flowchart is an appropriate
Q138: Highly customized job processes and processes that
Q139: A process chart activity that changes, creates,
Q140: The five categories of activities (operation, transportation,
Q142: Scenario 2.5
A job consists of three distinct
Q143: Scenario 2.3
A job consists of three elements.
Q144: Scenario 2.3
A job consists of three elements.
Q145: Garman observes a worker assembling peanut valves
Q146: A manager is interested in setting a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents