Solved

Champion Cooling Company Uses a Kanban System at Their Location

Question 137

Essay
Champion Cooling Company uses a kanban system at their location in the Oklahoma City Metroplex. The daily demand for fans is 2,000 and management insists on using an alpha level of 0.1. They use containers that hold 24 items and takes 0.02 of a day to process. It takes 0.08 of a day to get a container filled and for it to wait during its cycle. How many containers should they use? If they use the nearest integer value number of containers, what is the actual system alpha?

Champion Cooling Company uses a kanban system at their location in the Oklahoma City Metroplex. The daily demand for fans is 2,000 and management insists on using an alpha level of 0.1. They use containers that hold 24 items and takes 0.02 of a day to process. It takes 0.08 of a day to get a container filled and for it to wait during its cycle. How many containers should they use? If they use the nearest integer value number of containers, what is the actual system alpha?

Correct Answer:

verifed

Verified

k = blured image = blured image = 9.16 → 9 containers
...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents