Use the following partially completed MRP record to answer the question.
What are the quantities of planned order releases for item ABC for the first five weeks (weeks 1, 2, 3, 4, and 5) ?
A) 30, 0, 60, 0, 145
B) 60, 0, 145, 0, 0
C) 0, 30, 60, 0, 0
D) 30, 0, 60, 145, 0
Correct Answer:
Verified