Scenario 11.1
Sunshine Manufacturing produces three products: X, Y, Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A. End item Z is assembled from one unit of D and one unit of C; D is manufactured from one unit of A; and C is manufactured from one unit of B.
-Use the information in Scenario 11.1. If item C has a manufacturing lead time of two weeks, and a planned receipt of 65 units is needed in week 4, which of the following statements is True?
A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 4 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 2 is 65 units.
Correct Answer:
Verified
Q46: Which of the following statements about MRP
Q47: Which statement on MRP explosion is best?
A)
Q48: Which one of the following is a
Q49: Use the following partially completed MRP record
Q50: Management wishes to use an FOQ lot-sizing
Q52: Management wishes to use a POQ lot-sizing
Q53: Scenario 11.1
Sunshine Manufacturing produces three products: X,
Q54: Which one of the following is an
Q55: Use the following partially completed MRP record
Q56: MRP II ties MRP to the company's
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents