Question 167

Essay

A manufacturing plant is trying to determine standard production per day for an incentive program. Suppose that the incentive program will pay $1 per unit produced above standard rates. A worker is timed at an average of 280 seconds per unit, with a performance rating of 105%. The plant has an allowance factor of 13%. If the worker later produces 100 units in an 8 hour shift, how much would he receive under the incentive plan?

Correct Answer:

verifed

Verified

Standard time = (Average observed time ×...