A production line is to be designed to make 375 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. What is the required cycle time for this assembly line?
A) 0.5 minutes
B) 1.5 minutes
C) 2 minutes
D) 5,500 minutes
E) 4.26 minutes
Correct Answer:
Verified
Q292: In assembly-line balancing, cycle time (the ratio
Q293: Four hundred and eighty minutes of production
Q294: The central problem in product-oriented layout planning
Q295: The assumptions necessary for a successful product-oriented
Q296: Which of the following is NOT a
Q298: A production line is to be designed
Q299: Which of the following is one of
Q300: A production line is to be designed
Q301: Explain what the purpose of assembly-line balancing
Q302: A company is designing a product layout
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents