A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5.
A) The critical path is A-B-C, duration 9.
B) The critical path is A-B-C, duration 12.
C) The critical path is A-C, duration 10.5.
D) The critical path cannot be determined without knowing PERT expected activity times.
E) The network has no critical path.
Correct Answer:
Verified
Q55: The _ is a project management technique
Q56: The main difference between PERT and CPM
Q57: Every network has at most one critical
Q58: What is the basic difference between PERT
Q59: The ES of an activity that has
Q61: Explain why the critical path is the
Q62: The critical path for the network activities
Q63: The network below represents a project being
Q64: The network below represents a project being
Q65: Given the project within the table below,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents