The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
(a) What task must be on the critical path, regardless of activity durations?
(b) What is the duration of path A-B-E-H-J?
(c) What is the critical path of this network?
(d) What is the length of the critical path?
(e) What is slack time at activity H?
(f) What is the Late Finish of activity H?
(g) If activity C was delayed by six time units, what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q59: The ES of an activity that has
Q60: A simple CPM network has three activities,
Q61: Explain why the critical path is the
Q62: The critical path for the network activities
Q63: The network below represents a project being
Q65: Given the project within the table below,
Q66: What are the earliest activity start time
Q67: The following activities are part of a
Q68: The critical path for the network activities
Q69: The standard deviation of project duration is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents