Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
A) 0.04006
B) 0.45994
C) 0.80511
D) 0.95994
E) near 1.00000, or almost certain
Correct Answer:
Verified
Q110: PERT calculations typically include the duration variance
Q111: In PERT, project variance is computed by
Q112: In project management, crashing an activity must
Q113: Consider the network described in the table
Q114: Describe in words how to calculate a
Q116: Project management at the Tour de France
Q117: Which of the following statements regarding time-cost
Q118: A partially solved PERT problem is detailed
Q119: If an activity whose normal duration is
Q120: Shortening the project's duration by deleting unnecessary
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents