A partially solved PERT problem is detailed in the table below. Times are given in weeks.
(a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above.
(b) Which activities form the critical path?
(c) What is the estimated time of the critical path?
(d) What are the project variance and the project standard deviation?
(e) What is the probability of completion of the project before week 42?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q113: Consider the network described in the table
Q114: Describe in words how to calculate a
Q115: Contract requirements state that a project must
Q116: Project management at the Tour de France
Q117: Which of the following statements regarding time-cost
Q119: If an activity whose normal duration is
Q120: Shortening the project's duration by deleting unnecessary
Q121: Pirmin's Bike Shop is behind on a
Q122: Which of the following is NOT a
Q123: Three critical path activities are candidates for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents