Solved

Three Critical Path Activities Are Candidates for Crashing on a CPM

Question 123

Essay

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.    (a) What is the crash cost per unit time for each of the three activities? (b) Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? (c) Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? (a) What is the crash cost per unit time for each of the three activities?
(b) Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
(c) Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?

Correct Answer:

verifed

Verified

(a) crash cost X = $1,000 per ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents