Three critical path activities from the same critical path are candidates for crashing on a CPM network. Activity details are in the table below.
(a) What is the crash cost per unit time for activity A?
(b) What is the crash cost per unit time for activity B?
(c) Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
(d) Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
(e) Assuming no other paths become critical, how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q121: Pirmin's Bike Shop is behind on a
Q122: Which of the following is NOT a
Q123: Three critical path activities are candidates for
Q124: Given the critical path below, calculate the
Q125: A network has been crashed to the
Q127: Identify several advantages of using PERT (and
Q128: Which of the following is NOT performed
Q129: _ is decreasing activity time in a
Q130: If an activity whose normal duration is
Q131: Two activities on different critical paths that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents