Because direct costs are assumed to be developed from normal methods and in a normal amount of time, any reduction in activity time should ________ the direct cost of the activity.
A) decrease
B) increase
C) reduce
D) expand
E) approximate
Correct Answer:
Verified
Q73: Consider the following table of activities that
Q74: In order to shorten the duration of
Q75: A project that has several near-critical or
Q76: When crashing a schedule, this may set
Q77: Reducing the duration of an activity is
Q79: Compressing activities on a project with a
Q80: The _ time for an activity represents
Q81: Consider the following table of activities that
Q82: Why is the project duration with the
Q83: Why should a project manager be cautious