In order to shorten the duration of a project the project manager should limit the choices of activities to just those that are on the __________.
A) shortest path
B) path with the greatest variability
C) critical path
D) path with the least amount of resources required
E) path with the most resources required
Correct Answer:
Verified
Q69: An insensitive project network has the benefit
Q70: Direct costs are assignable directly to a
Q71: Consider the following table of activities that
Q72: There are fewer options available for reducing
Q73: Consider the following table of activities that
Q75: A project that has several near-critical or
Q76: When crashing a schedule, this may set
Q77: Reducing the duration of an activity is
Q78: Because direct costs are assumed to be
Q79: Compressing activities on a project with a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents