When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
Correct Answer:
Verified
Q11: It is possible for a project network
Q12: Experience suggests that when there are multiple
Q13: The critical path is the shortest path
Q14: The WBS identifies dependencies, the sequencing of
Q15: An activity cannot begin until ALL preceding
Q17: It is acceptable for arrows to cross