Question 1
True/False
A merge activity is one that merges with other activities into a succeeding activity.
Question 2
True/False
An activity can include only one work package.
Question 3
True/False
The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project.
Question 4
True/False
An activity is an element of the project that always requires time.
Question 5
True/False
Different activities along the same path can have different total slack.
Question 6
True/False
The backward pass determines project duration.
Question 7
True/False
Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
Question 8
True/False
If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.
Question 9
True/False
Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.
Question 10
True/False
In developing a project network, neither looping nor conditional statements are permitted.
Question 11
True/False
It is possible for a project network to have more than one critical path.
Question 12
True/False
Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.