If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
A) Check to see which activities cost the least.
B) Check to see which activities have the longest duration.
C) Check to see which activities are on the critical path.
D) Check to see which activities have the most slack.
E) Check to see which activities have the highest risk.
Correct Answer:
Verified
Q44: When creating a project network, your primary
Q45: The assumption that all immediately preceding activities
Q46: The backward pass in project network calculations
Q47: Which of the following will correctly calculate
Q48: The likelihood the original critical path(s) will
Q50: A project network provides the basis for
A)
Q51: Which of the following correctly calculates the
Q52: The minimum amount of time a dependent
Q53: The requirement for a freshly poured foundation
Q54: Which of the following is true about
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents