Question 41
Multiple Choice
If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
Question 42
Multiple Choice
A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, the purchasing agent has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. The purchasing agent and the installer share 10 days of
Question 43
Multiple Choice
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Question 44
Multiple Choice
When creating a project network, your primary input source will be the
Question 45
Multiple Choice
The assumption that all immediately preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
Question 46
Multiple Choice
The backward pass in project network calculations determines all of the following EXCEPT
Question 47
Multiple Choice
Which of the following will correctly calculate the total slack in an activity?
Question 48
Multiple Choice
The likelihood the original critical path(s) will change once the project is initiated is referred to as
Question 49
Multiple Choice
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
Question 50
Multiple Choice
A project network provides the basis for
Question 51
Multiple Choice
Which of the following correctly calculates the early finish for an activity?
Question 52
Multiple Choice
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
Question 53
Multiple Choice
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
Question 54
Multiple Choice
Which of the following is true about hammock activities?
Question 55
Multiple Choice
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a