When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
A) the smallest LS of all its immediate successor activities to establish the LF.
B) the largest ES of all its immediate successor activities to establish the LF.
C) the average LS of all its immediate successor activities to establish the LF.
D) the smallest ES of all its immediate successor activities to establish the LF.
E) the largest LS of all its immediate successor activities to establish the LF.
Correct Answer:
Verified
Q55: If a project has more than one
Q56: Which of the following correctly calculates the
Q57: Concurrent engineering, which has dramatically reduced the
Q58: The forward pass in project network calculations
Q59: The amount of time an activity can
Q61: A _ activity is one that has
Q62: An activity that has more than one
Q63: The amount of delay within a task
Q64: A _ activity is one that has
Q65: Activities that can occur while another activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents