The Delaying of Any Activity on the __________ Will Delay

Question 73

Multiple Choice

The delaying of any activity on the __________ will delay the completion of the project by the same amount.


A) network
B) critical path
C) WBS
D) gantt chart
E) responsibility assignment matrix

Correct Answer: