For any activity that has one or more predecessors, the ________ time is always the largest early finish of any of its predecessors. If the early finish times of an activity's predecessors were 85, 70 and 55, then this time would be the largest of these three early finish times or 85.
A) early finish
B) late finish
C) early start
D) late start
E) free slack
Correct Answer:
Verified
Q72: In a project network, _ indicate activity
Q73: The delaying of any activity on the
Q74: A(n) _ activity has more than one
Q75: An element in the project that consumes
Q76: One piece of information that the arrows
Q78: After the total slack for each activity
Q79: A _ activity is one that has
Q80: Activities that must immediately follow a given
Q81: A network has only one critical path
Q82: Consider the following table of activities A
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents