Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?
A) Estimates should be made by those responsible for the work.
B) Use several people to estimate the same work.
C) Estimates should be based on normal conditions.
D) Estimates should include a normal level of contingency.
E) Estimates should be independent of other projects.
Correct Answer:
Verified
Q37: Which of the following is a good
Q38: General and administrative costs are usually allocated
Q39: Which of the following is NOT one
Q40: In practice, estimating processes are frequently classified
Q41: Refining estimates may be necessary for a
Q43: When work package estimates are made by
Q44: Estimating can be challenged by
A) human nature.
B)
Q45: The estimating factor that considers the prevailing
Q46: While it may be true that Mega
Q47: Refining estimates may be necessary for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents