When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used.
A) top-down
B) analogous
C) bottom-up
D) reference class
E) professional estimation
Correct Answer:
Verified
Q38: General and administrative costs are usually allocated
Q39: Which of the following is NOT one
Q40: In practice, estimating processes are frequently classified
Q41: Refining estimates may be necessary for a
Q42: Which of the following is NOT one
Q44: Estimating can be challenged by
A) human nature.
B)
Q45: The estimating factor that considers the prevailing
Q46: While it may be true that Mega
Q47: Refining estimates may be necessary for a
Q48: The pattern of improvement identified from a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents