Which of the following is least likely to be included in a work package?
A) How long the work package should take to complete
B) A description of work to be performed
C) Overhead expenses
D) How much the work package should cost to complete
E) The person responsible for the work package
Correct Answer:
Verified
Q37: Responsibility Matrices are useful for assigning and
Q38: A typical responsibility matrix will include not
Q39: The ability of a 911 emergency system
Q40: "To construct a high-quality, custom home within
Q41: All of the following are usually included
Q43: All of the following are ways the
Q44: The integration of the lowest level of
Q45: The highest element in the hierarchical breakdown
Q46: The lowest element in the hierarchical breakdown
Q47: A Process Breakdown Structure can provide a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents