A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,


A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents