A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,
A) the project will currently finish under budget, assuming the project continues to perform in this way.
B) the project will currently finish over budget, assuming the project continues to perform in this way.
C) the project will currently finish on budget, assuming the project continues to perform in this way.
D) the project will currently finish behind schedule, assuming the project continues to perform in this way.
E) there is insufficient information to draw conclusions.
Correct Answer:
Verified
Q30: The final step in the project control
Q31: The third step in the project control
Q32: Although it is very difficult to measure,
Q33: A Control Chart can be used to
Q34: Deciding what data to collect, collecting the
Q36: A tool used to monitor past project
Q37: The earned value system starts with the
Q38: If the cost of labor and materials
Q39: In monitoring project time (schedule) performance, actual
Q40: The schedule variance is the best way
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents