A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a
A) Gantt chart.
B) network diagram.
C) PERT chart.
D) milestone chart.
E) project control chart.
Correct Answer:
Verified
Q31: The third step in the project control
Q32: Although it is very difficult to measure,
Q33: A Control Chart can be used to
Q34: Deciding what data to collect, collecting the
Q35: A project manager just received the following
Q37: The earned value system starts with the
Q38: If the cost of labor and materials
Q39: In monitoring project time (schedule) performance, actual
Q40: The schedule variance is the best way
Q41: Which of the following methods of variance