The Big Time Construction Company Is Erecting a Large Office

Question 1

Multiple Choice

The Big Time Construction Company is erecting a large office tower for a major commercial property developer. In the course of construction, a dispute arises as to the timing of cash advances from the developer to finance the next stage of construction. The parties had executed a contract between them which stated that each cash advance from the developer would be provided to the builder after the work on the previous stage had been completed and inspected by the developer. The builder now says that the developer is delaying the inspections and that it cannot carry on to the next stage without the cash advance. The developer says that the builder is deliberately delaying the progress of the construction by not beginning the next stage while it waits for the inspection required to release the next cash advance. The developer intends to take legal action against the builder.


A) The developer must use procedural law to sue the builder.
B) The dispute between the parties will be resolved by substantive law.
C) The contract which the parties made will be interpreted by private law.
D) The court will reach a decision in the case using administrative law.
E) All types of law except administrative law will apply.

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents