There Are Four Resources and Four Jobs to Be Done

Question 65

Multiple Choice

There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:   After the row and column reductions, what is the resulting entry in the new table for assigning resource 4 to job D? A) 0 hours B) 2 hours C) 3 hours D) 6 hours E) 9 hours
After the row and column reductions, what is the resulting entry in the new table for assigning resource 4 to job D?


A) 0 hours
B) 2 hours
C) 3 hours
D) 6 hours
E) 9 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents