The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?
A) 7.5 hours
B) 5 hours
C) 3 hours
D) 2.5 hours
E) 2 hours
Correct Answer:
Verified
Q58: Organizations with fixed, perishable capacity can benefit
Q59: A work center can be a:
(I)machine.
(II)group of
Q60: The scheduling sequencing rule which always results
Q61: The president of a consulting firm wants
Q62: One disadvantage of appointment systems is
A)Capacity can
Q64: In an assignment model where there are
Q65: There are four resources and four jobs
Q66: The president of a consulting firm wants
Q67: There are four resources and four jobs
Q68: The president of a consulting firm wants
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents