The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
What is the optimum sequence (first car to last) ?
A) A; B; C; D; E
B) E; D; C; B; A
C) E; B; D; C; A
D) E; D; B; C; A
E) E; B; D; A; C
Correct Answer:
Verified
Q85: The owner/operator of the local franchise of
Q86: High-volume jobs that often follow the same
Q87: Eva, the owner of Eva's Second Time
Q88: Job X, which has a duration of
Q89: Which costs depend on the order in
Q91: Which of the following is least likely
Q92: The owner/operator of the local franchise of
Q93: The operations manager of a body and
Q94: The operations manager of a body and
Q95: Job X arrived at work center Q
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents