Which of the following options is the CORRECT interpretation of a project appraisal that returns a Net Present Value of £3,500?
A) The project earns £3,500 more than the discount rate
B) The project earns £3,500 less than the discount rate
C) The project has a total cost of £3,500
D) The project has a total profit of £3,500
Correct Answer:
Verified