Multiple Choice
A resource requirements plan illustrates
A) who is responsible for which activities.
B) the amount of labour expenses for the project.
C) the expected utilisation of resources by time period during the time span of the project.
D) the budget for material and cost resources.
Correct Answer:
Verified