Resource-limited scheduling is a method for
A) developing a schedule that attempts to minimise the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
Correct Answer:
Verified