Olette Staines Limited produced and sold 1350 units of their OS211 product in September 20X7.Each unit was budgeted to use 1.5 hours of labour at a standard cost of £11.60 per hour.When the company's management accountant reviewed the records for the month he found that 1.6 labour hours had been used in actual production, at an actual cost of £11.55 per hour. What was the labour efficiency variance for September 20X7?
A) £1458 (F)
B) £1566 (A)
C) £1566 (F)
D) £1458 (A)
Correct Answer:
Verified
Q20: Sloop Warrenby Limited has the following budget
Q21: Vilneuve and Prewitt Limited's direct labour budget
Q22: Millworth and Moorhead Limited incurs variable production
Q23: Brookworth and Ghent Limited incurs variable production
Q24: Ancona and Flight Limited's direct labour budget
Q25: Parnassus Products Limited's labour budget for January
Q26: Sopworth and Barking Limited incurs variable production
Q28: Munster and Moss Limited budgeted sales and
Q29: Coromandel and Wellington Limited incurs variable production
Q30: Durkheim Goldfinger Limited budgeted a sales and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents