Munster and Moss Limited budgeted sales and production of 1650 units in the month of July 20X2.In the event, the company produced and sold 1665 units.The budgeted labour rate per unit was £12.50, whereas the actual rate was £12.40. Budget labour hours per unit of product was 4.3 hours, whereas actual the actual labour hours figure was 4.6 per unit.
What was the labour efficiency variance for July 20X2?
A) £6187.50
B) £5477.85
C) £6139.80 (A)
D) £6243.75 (A)
Correct Answer:
Verified
Q20: Sloop Warrenby Limited has the following budget
Q21: Vilneuve and Prewitt Limited's direct labour budget
Q22: Millworth and Moorhead Limited incurs variable production
Q23: Brookworth and Ghent Limited incurs variable production
Q24: Ancona and Flight Limited's direct labour budget
Q25: Parnassus Products Limited's labour budget for January
Q26: Sopworth and Barking Limited incurs variable production
Q27: Olette Staines Limited produced and sold 1350
Q29: Coromandel and Wellington Limited incurs variable production
Q30: Durkheim Goldfinger Limited budgeted a sales and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents