A project's asset beta is 1.15 and the relevant risk-free rate is 6%. The equity premium is expected to be 9%. The cost of capital for the project is


A) 23.25%.
B) 16.35%
C) 9.45%.
D) unable to be determined without knowing the amount of debt that will be used to finance the project.