A project has an asset beta of 0.70. The expected return on the market is 18%, and the relevant risk-free rate is 7%. The project's required rate of return is
A) 14.7%.
B) 10.5%.
C) 24.5%.
D) 19.6%.
Correct Answer:
Verified